Lead Times
This page provides an overview of typical lead times for the range of Caradon Stone products. Lead times are shown as average ranges and are intended as a guide to help with early-stage planning for projects.
Please note: Lead times can vary depending on availability, stock levels, quarry schedules, seasonal demand, weather conditions, and any bespoke requirements.
To make it easy, we’ve provided our lead time information product types. If you still require support, please get in touch with our team.
Page Navigation :
Exterior Stone
Typical uses: building stone, exterior cladding, architectural elements, bespoke exterior stonework.
| Product Type | Av. Lead Time (Cornwall) | Av. Lead Time (National) |
|---|---|---|
| Cornish Slate (Exterior) | 4–8 weeks | 4–8 weeks |
| Cornish Granite (Exterior) | 6–10 weeks | 6–10 weeks |
| Bespoke Exterior Stone | 8–14 weeks | 8–14 weeks |
Notes:
- Exterior products are more exposed to seasonal and weather-related variation.
- Quarry output and block availability can influence timescales, particularly for large or matched order
Interior Stone
Typical uses: flooring, internal walling, hearths, stair treads, interior architectural features.
| Product Type | Av. Lead Time (Cornwall) | Av. Lead Time (National) |
|---|---|---|
| Interior Slate Flooring | 3–6 weeks | 3–6 weeks |
| Interior Granite Flooring | 4–8 weeks | 4–8 weeks |
| Cut-to-Size / Bespoke Interior Orders | 6–12 weeks | 6–12 weeks |
Notes:
- Interior products often have more consistent lead times than exterior stone.
- Bespoke finishes, specific thicknesses, or tighter tolerances may extend production time.
Garden & Landscaping
Typical uses: paving, walling, steps, kerbs, edging, landscaping features
| Product Type | Av. Lead Time (Cornwall) | Av. Lead Time (National) |
|---|---|---|
| Slate Paving | 3–6 weeks | 3–6 weeks |
| Granite Paving | 4–8 weeks | 4–8 weeks |
| Walling Stone | 4–8 weeks | 4–8 weeks |
| Bespoke Landscaping Elements | 6–12 weeks | 6–12 weeks |
| Landscaping Boulders | 2–4 weeks | 2–4 weeks |
| Gateposts | 2–4 weeks | 2–4 weeks |
Notes:
- Spring and summer demand can increase lead times for landscaping products.
- Larger paving quantities may require phased production.
What Affects Lead Times
Lead times shown above are averages and are provided as a guide only. Actual delivery times may vary depending on a number of factors, including quarry capacity and extraction schedules, the availability of suitable stone blocks, seasonal demand, particularly during the spring and summer months, weather conditions that can affect quarrying and processing, current stock levels of finished or semi-finished products, and any bespoke requirements such as non-standard sizes, finishes, or stone matching.
Fast-Track Options
For trade customers requiring shorter timescales:
- Fast-track delivery may be available for products that are in stock or immediately available. Fast-track delivery is available nationwide.
- 24-hour delivery service our team is able to organise 24-hour delivery service for a number of our products. This service is available nationwide.
Costs for quicker delivery can vary depending on product type, quantity, and location. Please get in touch with our team to discuss availability and costs.
Collections
We are pleased to be able to offer a collection service at our Cornwall-based quarry, Lantoom.
Collections are available by appointment and are applicable to in-stock products only.
Collection times and loading requirements will be confirmed prior to your visit.
If you are working to a specific programme or deadline, our team is always happy to advise on current availability and realistic lead times for your project.
Here to support your project
If you can’t find the information you need, our team is always happy to help. For technical queries, bespoke requests, or project-specific advice, please get in touch and speak to a member of our expert team.